  • Unit 1: Energy, Work and Power
    5
    • 1.1
      Pumped Storage: Work, Kinetic and Potential Energy
      50 mins
    • 1.2
      Ramp Lab: Measuring Energy Transfer and Efficiency
      100 mins
    • 1.3
      Where Did the Energy Go? Springs, Rubber Bands and Thermal Energy
      100 mins
    • 1.4
      Power and a Pumped-Storage Day: A Computational Energy Model
      100 mins
    • 1.5
      Performance Task — Design, Build and Refine an Energy Converter
      200 mins
  • Unit 2: Thermal Energy and the Second Law
    5
    • 2.1
      Why a Dark Roof Gets Hotter: Temperature, Thermal Energy and Heat
      50 mins
    • 2.2
      Specific Heat by the Method of Mixtures
      100 mins
    • 2.3
      Why Heat Flows Downhill: The Second Law and Engine Limits
      50 mins
    • 2.4
      Particles, Pressure, Heat Pumps and Insulating Materials
      100 mins
    • 2.5
      Performance Task — Keep It Cold in a Missouri Summer
      200 mins
  • Unit 3: Electricity and Magnetism
    5
    • 3.1
      Missouri Winter Sparks: Charge and Coulomb’s Law
      100 mins
    • 3.2
      Circuit Lab: Ohm’s Law, Series and Parallel with a Multimeter
      100 mins
    • 3.3
      Do Currents Make Magnetic Fields? Electromagnet Evidence and Argument
      100 mins
    • 3.4
      Fields, Induction and the Wind Turbines of Atchison County
      100 mins
    • 3.5
      Performance Task — Wind to Wire: Modeling a Transmission Link
      150 mins
  • Unit 4: Waves, Light and Information
    5
    • 4.1
      Seconds of Warning: Wave Speed and the New Madrid Seismic Zone
      50 mins
    • 4.2
      Investigation Lab: Standing Waves on a Stretched String
      100 mins
    • 4.3
      Argument Lab: Is Digital Always Better?
      50 mins
    • 4.4
      Light as Wave and Particle: Refraction, Photons and the Spectrum
      100 mins
    • 4.5
      Performance Task — Technical Brief: Waves That Carry Information and Energy
      150 mins
  • Unit 5: Missouri Physics Supplement
    3
    • 5.1
      Stars, Elements and the Big Bang
      50 mins
    • 5.2
      Earth’s Crust and Earth’s Story
      50 mins
    • 5.3
      Earth’s Energy and Feedbacks
      50 mins

Power and a Pumped-Storage Day: A Computational Energy Model

Unit 1  ·  Modeling & Explanation Workshop  ·  Lesson 4 of 23

Power and a Pumped-Storage Day: A Computational Energy Model

9-12.PS3.A.1RLP-PHYB
Cutaway pumped-storage facility showing water moving between reservoirs and an abstract spreadsheet model.
By the end of this lesson I can…

calculate power in several ways, convert between joules, kilowatt-hours and megawatt-hours, and build a spreadsheet model that tracks energy through a pumped-storage day and a skate track with friction.

Instruction

Power is the rate of energy transfer. Two cranes can lift the same load to the same height; the one that does it faster has more power: P = W/t = ΔE/t, measured in watts (1 W = 1 J/s). When a force F pushes something along at steady speed v, P = Fv.

  • A 55 kg student runs up a 3.2 m flight of stairs in 4.0 s: P = mgh/t = (55)(9.8)(3.2)/4.0 = 431 W, a little over half a horsepower (1 hp ≈ 746 W).
  • An 800 kg elevator rising at a steady 2.0 m/s needs P = Fv = mgv = 15,680 W. Check: lifting it 30 m in 15 s gives mgh/t = 15,680 W, the same.
  • A car at 25 m/s pushing against 500 N of air drag and rolling resistance needs 12.5 kW just to keep its speed.

Energy units at grid scale. The grid measures energy in kilowatt-hours: 1 kWh = (1000 J/s)(3600 s) = 3.6 × 106 J, and 1 MWh = 3.6 × 109 J. Power plants are rated in megawatts (MW); the energy they deliver is power times time.

A computational model of a pumped-storage day (illustrative schedule and efficiencies, Taum Sauk’s real head). A plant pumps at 300 MW from midnight to 06:00, when demand is low, and generates from 14:00 to 18:00, a summer-afternoon peak. Pump efficiency 85%, generator efficiency 84% (together Taum Sauk’s published 0.714), head 262 m.

  • Electricity used: 300 MW × 6 h = 1,800 MWh.
  • Stored as gravitational potential energy: 1,800 × 0.85 = 1,530 MWh.
  • Delivered at the peak: 1,530 × 0.84 = 1,285.2 MWh, an average of 321.3 MW over 4 h. Round trip: 71.4%.
  • Water moved: m = E/(gh) = (1,530 × 3.6 × 109 J)/((9.8)(262)) = 2.15 × 109 kg, about 2.15 million m3, or 38% of the 5.68 million m3 Taum Sauk’s upper reservoir holds.

A spreadsheet runs this hour by hour: column A the hour, B the mode (pump, idle, generate), C the electrical power, D the energy stored at the end of the hour (the previous value plus pumping × efficiency, or minus generation ÷ efficiency). The graph shows the result:

0481216202440080012001600hour of daystored energy (MWh)

Check the model against the real plant. The U.S. Energy Information Administration publishes Taum Sauk’s monthly output (Form EIA-923). In 2025 the plant generated 415,892 MWh gross, and its net generation was −159,810 MWh, because pumping used more electricity than generating returned. Its busiest month was July, with 63,628 MWh: about 2,050 MWh a day, or 4.7 hours a day at the full 440 MW, close to the model’s four-hour peak. This lesson’s reading has the whole year.

Once the model works, you can change one input and watch the output: a higher head stores the same energy in less water; better turbines raise the round trip. That is what makes it a computational model.

Energy accounting with friction. The same bookkeeping works for a skateboarder (60 kg) on a track with a steady 30 N of friction along it (illustrative numbers). At every point, PE + KE + thermal = the starting 2,940 J, where thermal = friction × distance traveled along the track:

PointHeight (m)Track distance from start (m)PE (J)Thermal (J)KE (J)Speed (m/s)
A (start)5.002,940000.00
B (bottom)0.0802402,7009.49
C (hump)2.0121,1763601,4046.84
D (end)0.5172945102,1368.44

At B, KE = 2,940 − 0 − 240 = 2,700 J, so v = √(2 × 2,700/60) = 9.49 m/s, compared with 9.90 m/s without friction. The total never changes; the thermal column only grows.

Common errors. Mixing kW and kWh (power versus energy); forgetting to convert hours to seconds; applying an efficiency twice or in the wrong direction (pumping multiplies by efficiency, drawing stored energy back out divides by it when you ask how much must be stored to deliver a given amount).

📖 Read for this lesson

The reading opens over the lesson; close it to come back to exactly where you were. The checks below draw on it.

  • A Real Pumped-Storage Year: Taum Sauk Month by Month in 2025, Beside the Lesson’s ModelEIA Form EIA-923, plant 2108 (Taum Sauk, Missouri), monthly gross and net generation for 2025, retrieved via the EIA API v2 (electricity/facility-fuel) November 5, 2026; Ameren Missouri, Taum Sauk Energy Center page and 2011 Integrated Resource Plan (EFIS 55215) for the reservoir volume, schedule and round trip; SLS model table · about 5 min

    Taum Sauk’s real month-by-month output for 2025 from EIA Form EIA-923, placed beside the lesson’s hour-by-hour computational model and its worked variants, so the modeling workshop tests its equations and its 71.4% round trip against an actual Missouri operating record.

Vocabulary in context

  • power — The rate of energy transfer, P = W/t; for a steady force at speed v, P = Fv; in watts.
  • kilowatt-hour (kWh) — The energy transferred by 1 kW in one hour, 3.6 × 106 J.
  • round-trip efficiency — Energy returned by a storage system divided by the energy put in.
  • computational model — A calculation, often in a spreadsheet, that predicts how a system responds to changed inputs.

Formative check

Work through these before moving on. They are not graded — they tell you whether the standard below has landed yet.

+50 XP

A 55 kg student climbs 3.2 m of stairs in 4.0 s. What is the average power?

P = mgh/t = (55)(9.8)(3.2)/4.0 = 431 W.
Fill in the blank

A plant pumps at 300 MW for 6 h with 85% efficiency, storing MWh. With 84% generator efficiency it later delivers MWh.

Myth or Fact?

A 300 MW plant and a 300 MWh battery describe the same kind of quantity.

MW is power, a rate. MWh is energy, a rate times a time. A 300 MW plant running for 2 h delivers 600 MWh.

Simulation & tools

Energy accounting with friction

Open the Friction screen. Turn on the Bar Graph and Speed, choose the 60 kg skater if available, and start the skater from rest at the top of the track with friction at zero. Record the speed at the bottom and compare with √(2gh). Then set friction to a middle value and watch the thermal bar: record how the kinetic, potential and thermal bars change over three passes. Question: does the total bar height ever change, and where does the lost kinetic energy go? No device: use the skate-track table in the lesson and add a column that checks PE + KE + thermal at every point.

Open in a new tab ↗  ·  PhET Interactive Simulations, University of Colorado Boulder · CC BY 4.0

Build the pumped-storage spreadsheet from the lesson. Then test two proposed improvements: (a) a site with a head of 300 m instead of Taum Sauk’s 262 m, and (b) better turbines with 90% generator efficiency. For each, report the round-trip efficiency and the volume of water needed. Which change helps the grid more, and which helps the reservoir size? Paste your table and graph (a calculator table is fine).

0 words
Quick self-check

How confident are you that you can calculate power and build a spreadsheet model that tracks energy through a system?

Not yetVery confident

Practice

Work these on paper or in your notebook, then open Check your answer. Aim for all of Fluency and Application; try at least one Challenge.

Printable version: this unit’s practice workbook (PDF)

Fluency

Build speed and accuracy with the core skill.

  1. A motor does 1500 J of work in 2 s. What is its power output?
    Check your answer
    Answer: 750.0 W
    P = W/t.
  2. A motor does 600 J of work in 4 s. What is its power output?
    Check your answer
    Answer: 150.0 W
    P = W/t.
  3. A motor does 12000 J of work in 4 s. What is its power output?
    Check your answer
    Answer: 3,000.0 W
    P = W/t.
  4. Convert 300 cm3 to mL.
    Check your answer
    Answer: 300.00 mL
  5. A 62 kg student climbs 4.5 m of stairs in 5.0 s. Find the power.
    Check your answer
    Answer: 547 W
    mgh/t.
  6. A 1.5 kW space heater runs for 3.0 h. How much energy does it use, in kWh and joules?
    Check your answer
    Answer: 4.5 kWh = 1.62 × 107 J
    E = Pt.

Application

Use the skill in context. Show your reasoning.

  1. A crane lifts 500 kg of steel 12 m in 20 s at steady speed. What is its output power?
    Check your answer
    Answer: 2,940 W
    mgh/t, or F v with v = 0.60 m/s.
  2. A car at 30 m/s faces 650 N of drag and rolling resistance. What power keeps it at that speed?
    Check your answer
    Answer: 19.5 kW
    P = Fv.
  3. A pumped-storage plant pumps at 250 MW for 5 h with 85% pump efficiency. How much energy is stored (MWh)?
    Check your answer
    Answer: 1,062.5 MWh
    250 × 5 × 0.85.

Challenge

Stretch problems. Expect to think before you write.

  1. The plant above delivers its stored energy with 88% generator efficiency over 3 h. What average power does it deliver, and what is the round-trip efficiency?
    Check your answer
    Answer: 311.7 MW; 74.8%
    1,062.5 × 0.88 = 935.0 MWh over 3 h; round trip 0.85 × 0.88.

Review

Keep earlier skills sharp.

  1. A net force of 2250.0 N gives an object an acceleration of 1.5 m/s2. What is its mass?
    Check your answer
    Answer: 1,500.00 kg
    m = Fnet/a.
  2. A car moving at 9 m/s speeds up at 1.5 m/s2 for 2 s. What is its final speed?
    Check your answer
    Answer: 12.0 m/s
    v = v0 + at.

Missouri Learning Standards — Science addressed: 9-12.PS3.A.1, 9-12.ETS1.B.2, SEP.2, SEP.5, CCC.4, RST.11-12.7, MP.4

Instructional focus: A spreadsheet model of energy flow and power in a real system, tested by changing inputs

Reading

A Real Pumped-Storage Year: Taum Sauk Month by Month in 2025, Beside the Lesson’s Model

EIA Form EIA-923, plant 2108 (Taum Sauk, Missouri), monthly gross and net generation for 2025, retrieved via the EIA API v2 (electricity/facility-fuel) November 5, 2026; Ameren Missouri, Taum Sauk Energy Center page and 2011 Integrated Resource Plan (EFIS 55215) for the reservoir volume, schedule and round trip; SLS model table · Public domain (works of the United States government), with published Ameren Missouri figures and SLS original worked tables

Why this reading. The lesson’s pumped-storage day is a model: pump at 300 MW from midnight to 06:00, generate from 14:00 to 18:00, with Taum Sauk’s real 262 m head and an illustrative 85%/84% split of its published 0.714 round trip. The open question asks you to build that model and change its inputs, and the true-or-false check turns on the difference between MW and MWh. Here is the model worked out hour by hour, so you can check a spreadsheet against it, and beside it a real year: Taum Sauk’s month-by-month output for 2025 as reported to the U.S. Energy Information Administration.

Table 1. Taum Sauk, 2025, month by month (EIA Form EIA-923)

Source: EIA Open Data API v2, electricity/facility-fuel, plant 2108 (Taum Sauk, Reynolds County, Missouri), prime mover “PS” (pumped storage), monthly gross and net generation, retrieved November 5, 2026. Columns 4 to 7 are SLS computations. Electricity in = gross − net (pumping plus the plant’s own station use). Hours a day at full output = (gross ÷ days in the month) ÷ 440 MW. EIA revises recent plant data, so a later download may differ slightly.

MonthGross generation (MWh)Net generation (MWh)Electricity in (MWh)Fraction returnedAverage gross per day (MWh)Hours a day at 440 MW
January30,511−12,57043,08170.8%9842.2
February26,260−10,83137,09170.8%9382.1
March30,003−10,08540,08874.8%9682.2
April16,233−5,72721,96073.9%5411.2
May17,870−6,88324,75372.2%5761.3
June58,955−22,05881,01372.8%1,9654.5
July63,628−24,33887,96672.3%2,0534.7
August53,094−21,05374,14771.6%1,7133.9
September52,684−19,40372,08773.1%1,7564.0
October23,173−9,16732,34071.7%7481.7
November18,470−7,15325,62372.1%6161.4
December25,011−10,54235,55370.3%8071.8
2025415,892−159,810575,70272.2%1,1392.6

Two patterns stand out. First, the fraction returned barely moves: every month sits between 70% and 75%, beside Ameren’s published 0.714. The round trip is a property of the machines and the water, not of the season. Second, the amount moves a great deal. June through September each produced more than 50,000 MWh; April and May produced less than 18,000. In July the plant averaged 2,053 MWh a day, about 4.7 hours at full output; in April, about 1.2 hours. The plant runs when demand is greatest, and in Missouri that means summer.

Table 2. The lesson’s model, hour by hour

Pump 300 MW from 00:00 to 06:00 at 85%; generate from 14:00 to 18:00 at 84%; head 262 m. Column 4 is the energy stored at the end of the hour: the previous value plus 300 × 0.85 = 255 MWh in each pumping hour, minus 321.3 ÷ 0.84 = 382.5 MWh in each generating hour.

HourModeElectrical power (MW)Stored at end of hour (MWh)
00:00-01:00pump300255.0
01:00-02:00pump300510.0
02:00-03:00pump300765.0
03:00-04:00pump3001020.0
04:00-05:00pump3001275.0
05:00-06:00pump3001530.0
06:00-07:00idle01530.0
07:00-08:00idle01530.0
08:00-09:00idle01530.0
09:00-10:00idle01530.0
10:00-11:00idle01530.0
11:00-12:00idle01530.0
12:00-13:00idle01530.0
13:00-14:00idle01530.0
14:00-15:00generate321.31147.5
15:00-16:00generate321.3765.0
16:00-17:00generate321.3382.5
17:00-18:00generate321.30.0
18:00-19:00idle00.0
19:00-20:00idle00.0
20:00-21:00idle00.0
21:00-22:00idle00.0
22:00-23:00idle00.0
23:00-24:00idle00.0

Checks: electricity used 300 × 6 = 1,800 MWh; stored 1,800 × 0.85 = 1,530 MWh; delivered 1,530 × 0.84 = 1,285.2 MWh, an average of 321.3 MW over four hours; round trip 1,285.2 ÷ 1,800 = 71.4%. Water moved: m = E/(gh) = (1,530 × 3.6 × 109 J)/((9.8)(262)) = 2.15 × 109 kg, about 2.15 million m3, or 38% of the 5.68 million m3 (1.5 billion gallons) Ameren says the upper reservoir holds.

Worked variants for the open question

(a) A head of 300 m instead of 262 m. The efficiencies do not change, so the energies and the 71.4% round trip do not change. Only the water does: (1,530 × 3.6 × 109)/((9.8)(300)) = 1.87 × 109 kg, about 1.87 million m3: 12.7% less water for the same energy, so a smaller upper reservoir.

(b) Generator efficiency raised to 90%. Delivered energy 1,530 × 0.90 = 1,377 MWh, average power 344.25 MW, round trip 1,377 ÷ 1,800 = 76.5%. The water is unchanged at 2.15 × 109 kg. This is the change the grid notices; (a) is the change the reservoir notices.

Reading the real year against the model

The model’s day delivers 1,285.2 MWh. Taum Sauk’s average July day delivered 2,053 MWh. At the model’s 84% generator efficiency and 262 m head, that is (2,053 ÷ 0.84) × 3.6 × 109 ÷ (9.8 × 262) = 3.43 × 109 kg of water, about 3.43 million m3 a day run down the mountain and pumped back up, roughly 60% of the upper reservoir. Notice what the monthly record does not show: the hours. EIA-923 reports months, not days, so the model’s schedule (pump overnight, generate in the afternoon) comes from Ameren’s description of how the plant is run, not from these numbers. A model that shows both sides of the ledger, hour by hour, tells you things a monthly total cannot.

Your turn

  1. From Table 1, compute the average power of Taum Sauk’s generation over the whole of July 2025 (all 744 hours), and the average power if all of July’s output came in 4.7 hours a day. Explain why the same MWh gives such different MW.
  2. Build Table 2 in a spreadsheet or by hand and reproduce every value in the stored-energy column. Then run variants (a) and (b) and confirm the figures above.
  3. Change the model so that it pumps for 8 hours at 300 MW. How much energy is stored, how long can the plant then generate at 440 MW, and is that more or less than the 4,050 MWh a full upper reservoir can hold?
  4. A 440 MW plant and a 440 MWh battery: using July’s average day, say how many hours of Taum Sauk’s July output each could supply on its own, and what extra information you would need about the battery.

Sources: EIA Open Data API v2, electricity/facility-fuel (Form EIA-923), plant 2108 Taum Sauk, annual and monthly net and gross generation (api.eia.gov); EIA, Form EIA-923 detailed data (eia.gov); Ameren Missouri, Taum Sauk Energy Center (ameren.com); Ameren Missouri, 2011 Integrated Resource Plan, Chapter 5: Renewable and Storage Resources (EFIS 55215) (efis.psc.mo.gov)

Up NextComplete & Continue →

Leave a Reply Cancel reply

Where Did the Energy Go? Springs, Rubber Bands and Thermal Energy
Prev
Performance Task — Design, Build and Refine an Energy Converter
Next